Solar PV grants and incentives for public bodies

For a public body the main national route is the GSE's Conto Termico 3.0: it covers solar PV only if you install it together with replacing the heating system with an electric heat pump, up to 20% of the eligible cost for the solar part. A municipality can also join a renewable energy community and make its roofs and land available.

Updated on official sources checked

Try:
  • 2

    incentives open today

  • 31 December 2027

    next deadline: GSE premium tariff for shared energy

  • 20%

    of the solar PV cost under Conto Termico 3.0, only together with an electric heat pump

  • 3 of 4

    entries checked against official sources

Each row takes you to its section. Greyed-out entries are being checked: we show what is missing and no figures.

Status
Type

4 incentives shown

Summary table of the incentives: incentive, who can claim it, how much it is worth, closing date, status
IncentiveWho can claim itHow muchClosesStatus
Conto Termico 3.0Public bodies, third-sector bodies and private applicants on service-sector buildings20% of the solar PV cost, only with an electric heat pumpno closing dateOpen
GSE premium tariff for shared energy (energy communities and distributed self-consumption)Distributed self-consumption configurations: CERs, groups of self-consumers, remote self-consumersPremium tariff for 20 years on shared energy: a fixed part of 60 to 80 euros/MWh depending on size, plus a variable part of up to 40 euros/MWh31 December 2027Open
Recovery plan non-repayable grant for CERs and groups of self-consumers in municipalities under 50,000 residentsCERs and groups of self-consumers with systems in municipalities under 50,000 residents (applications closed)Up to 40% of the eligible costs (applications closed on 30 November 2025)30 November 2025Closed
PREPAC - energy upgrading of central government buildings—Being checked—Being checked

The incentives in detail

Open an entry for requirements, steps, documents and mistakes to avoid. Every entry carries its official sources at the end.

OpenNon-repayable grant

Conto Termico 3.0

The GSE's Conto Termico 3.0 pays for solar PV only if you install it together with replacing the existing heating with an electric heat pump. For the solar part the grant reaches 20% of the eligible cost, within the maximum costs set by the decree, and it cannot exceed the grant for the heat pump.Worth: 20% of the solar PV cost, only with an electric heat pumpCloses: No fixed deadline: applications close 60 days after spending commitments reach the annual limit set for the category.
Show the details

Who can claim it

  • Public administrations: they can apply for every measure in the decree, solar PV included.
  • Third-sector bodies listed in the RUNTS (the national register of the third sector) that carry out no economic activity: they are treated like public administrations.
  • Third-sector bodies carrying out economic activity, and businesses: for solar PV only on service-sector buildings, under the rules specific to businesses.
  • Private applicants: for solar PV only on service-sector buildings.
  • The body can be represented by an ESCO (an energy services company) under an energy performance contract, by another public body managing the properties, by a private partner under a public-private partnership, or by an energy community (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.) it belongs to.
Who is excluded
  • Solar PV on its own: without replacing the heating with an electric heat pump it does not qualify.
  • Private homes: for private applicants solar PV is not eligible on residential buildings, so it does not cover solar PV on your house.
  • Buildings with no existing heating system.
  • Work receiving other state incentives, except where the rules allow it for public administration buildings.

How much it is worth

  • Solar part: up to 20% of the eligible costs, within a maximum cost per system and storage (Batteries that store the energy produced during the day so you can use it when the system is not producing.) size set by the decree.
  • The grant for solar PV cannot exceed the grant awarded for the heat pump installed alongside it.
  • An uplift of 5, 10 or 15 percentage points if all the modules are listed in the register of photovoltaic technologies, depending on the section of the register.
  • General Conto Termico cap: 65% of the eligible costs. It rises to 100% for buildings owned and used by municipalities of up to 15,000 residents and for public schools, hospitals and healthcare facilities, always within the ceilings for each type of work.
  • Energy audits and energy performance certificates linked to the work: covered at 100% for public administrations.
  • For the energy audit, public administrations and non-economic third-sector bodies can apply for an advance grant equal to 50% of the cost to be incurred.
  • 2026 funds: 450 million euros for public administration projects, out of 900 million euros a year in total.

Eligible costs

  • Supply and installation of the solar PV system and of any storage system (Batteries that store the energy produced during the day so you can use it when the system is not producing.), including grid connection costs.
  • Professional services linked to the work.
  • VAT is included in the eligible cost only where it is a cost for the applicant.

Requirements for solar PV

  • It must be carried out together with replacing the existing heating system with an electric heat pump serving the same building.
  • The system sits on the building or on its appurtenances as shown in the land-registry record.
  • The system works for self-consumption (The energy the system produces and you use on site, instead of feeding it into the grid.) (partial feed-in of the energy to the grid).
  • Capacity from 2 kW to 1 MW, and in any case no more than the capacity available at the delivery point.
  • Annual output cannot exceed the building's average annual consumption, electrical and thermal, by more than 5%.
  • New modules and inverters with CE marking; modules with a product warranty of at least 10 years and a performance warranty of at least 90% after 10 years; inverters with a guaranteed European efficiency of at least 97%.
  • At the time of the application the system must be connected to the grid, or installed with the connection procedure already started.
  • For businesses and economic third-sector bodies: a reduction in primary energy demand of at least 20%, shown with an energy performance certificate before and after.

Combining it with other incentives

  • General rule: it cannot be combined with other state incentives, except guarantee funds, revolving funds and interest subsidies.
  • For buildings owned and used by the public administration it can be combined with other public incentives and funding, up to total non-repayable (A grant that does not have to be paid back.) support of 100% of the eligible costs.
  • It can be combined with renewable energy communities (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.) and collective self-consumption (The energy the system produces and you use on site, instead of feeding it into the grid.) within the limits of article 6 of MASE decree 414 of 7 December 2023.

How to apply

  1. 1Register in the GSE Customer Area. Whoever bears the cost (the body, or the ESCO acting for it) registers and selects the Conto Termico 3.0 service on the Portaltermico.
  2. 2Choose between direct access and advance booking. With direct access you claim the grant once the work is finished, within 90 days of completion. Advance booking, reserved for public administrations and third-sector bodies, is requested before or during the work and needs at least one of these: an energy audit, an energy performance contract, a public-private partnership contract or other integrated contract, or a deed awarding the work with a handover record.
  3. 3With advance booking: report the start of the work. After the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.)'s acceptance letter you upload the documents on the start and the award of the work to the Portaltermico. If the assessment is positive the GSE pays an amount on account: two fifths of the grant if it runs over five years, half if it runs over two.
  4. 4Finish the work and claim the balance. You report that the work is finished and, within 90 days, claim the balance through direct access. On request, after the work has started, you can also receive an intermediate instalment tied to progress.
  5. 5Receive the grant. With direct access the public administration receives the grant in a single instalment. Up to 15,000 euros payment is always in a single instalment.

Documents

  • Technical and identifying details of the work uploaded to the Portaltermico, with the signed application form and contract form and an identity document.
  • For advance booking: an energy audit, or an energy performance contract, a partnership contract or a deed awarding the work with a handover record.
  • For the 100% rate in municipalities of up to 15,000 residents: a declaration on the population threshold, the land-registry record of the municipal building and, if the building is used by others, the title proving it.
  • For the uplift tied to the register: documentation showing the modules are listed in the register of photovoltaic technologies.
  • For businesses and economic third-sector bodies: an energy performance certificate before and after the work.

Mistakes that cost you the benefit

  • Applying for solar PV on its own: without the electric heat pump replacing the old heating, the application is not eligible.
  • Sizing the system above your consumption: output cannot exceed the building's average annual consumption by more than 5%.
  • Going beyond 90 days from the end of the work for direct access or for the balance claim.
  • Mixing modules from different sections of the register: the uplift is then not due.
  • Losing the requirements after being paid: they must be kept for the whole incentive period and for the five years after the last instalment, otherwise the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.) claws the money back.
  • Taking it for granted that advance booking is available: before counting on it, check on the Portaltermico which routes are open.

Example: on an eligible solar PV cost of 100,000 euros

A municipality with more than 15,000 residents replaces the town hall boiler with an electric heat pump and, at the same time, installs a solar PV system on the roof. For the solar part alone the grant reaches at most 20% of the eligible cost. The sum holds if the cost falls within the maximum costs per size set by the decree and if the grant for the heat pump is not lower.

On an eligible solar PV cost of 100,000 euros
Eligible cost for the solar PV100,000 euros
Percentage for the solar PV20%
Maximum grant for the solar PV20,000 euros
Limitno more than the grant for the paired heat pump

Official sources

  • Gazzetta Ufficiale — Decreto MASE 7 agosto 2025 (GU Serie Generale n. 224 del 26 settembre 2025), artt. 3, 4, 5 comma 1 lettera h), 10, 11, 17 e 31
  • GSE — Regole Applicative del D.M. 7 agosto 2025, approvate il 19 dicembre 2025, paragrafi 4.2 e 9.8
  • GSE — Conto Termico 3.0 — Percentuali ed erogazione degli incentivi
  • GSE — Conto Termico 3.0 — Come accedere (accesso diretto e prenotazione)
  • GSE — Conto Termico 3.0 — Chi può accedere
  • GSE — News del 13 aprile 2026: decreto direttoriale MASE n. 72 del 10 aprile 2026, limiti di spesa 2026

Checked on 19 November 2026

OpenFeed-in tariff

GSE premium tariff for shared energy (energy communities and distributed self-consumption)

If your solar PV system is part of a renewable energy community (CER), of a group of self-consumers, or is a remote self-consumer, the GSE pays a premium tariff on the shared energy for 20 years. You can apply until 31 December 2027, or earlier if 5 GW of incentivised capacity is reached.Worth: Premium tariff for 20 years on shared energy: a fixed part of 60 to 80 euros/MWh depending on size, plus a variable part of up to 40 euros/MWhCloses: 31 December 2027
Show the details

It can be applied for up to the thirtieth day after 5 GW of incentivised capacity is reached, and in any case no later than 31 December 2027. The application must be filed within 120 days of the system entering service.

Who can claim it

  • Renewable energy communities (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.) (CER): members or shareholders can be individuals, small and medium-sized businesses (SMEs), associations, third-sector bodies, religious bodies, research bodies and local authorities.
  • SMEs can take part in a CER (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.) only if that participation is not their main commercial or industrial activity.
  • Groups of self-consumers (for example in an apartment building or in a building with a single owner).
  • Remote self-consumers (a single customer using the energy from their own system sited elsewhere, under the same primary substation).
  • The application is filed by the configuration's Referent (the CER (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.) itself, the apartment building through its manager, the self-consumer) or, under a mandate, by a member of the configuration or by an ESCO certified to UNI 11352.
Who is excluded
  • Large businesses cannot be members or shareholders of a CER (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.).
  • Central government bodies cannot be members or shareholders of a CER (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.).
  • Private businesses whose main ATECO code is 35.1, 35.11.00, 35.12.00 or 35.15.00 cannot be members or shareholders of a CER (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.).
  • Businesses in difficulty and businesses with an outstanding State aid recovery order.
  • Systems with capacity above 1 MW: they only receive the valorisation payment on self-consumed (The energy the system produces and you use on site, instead of feeding it into the grid.) energy, not the premium tariff.
  • The share of capacity installed to meet the renewables obligation in new or renovated buildings (the so-called mandatory capacity) does not receive the premium tariff.

How much it is worth

  • The premium tariff has a fixed part that depends on the system's capacity and a variable part that rises when the zonal energy price (the wholesale market price in your zone) falls below 180 euros/MWh.
  • Systems up to 200 kW: 80 euros/MWh plus the variable part, capped at 120 euros/MWh.
  • Systems above 200 kW and up to 600 kW: 70 euros/MWh plus the variable part, capped at 110 euros/MWh.
  • Systems above 600 kW: 60 euros/MWh plus the variable part, capped at 100 euros/MWh.
  • For solar PV there is a geographical uplift: +4 euros/MWh in the central Regions (Lazio, Marche, Toscana, Umbria, Abruzzo) and +10 euros/MWh in the northern Regions (Emilia-Romagna, Friuli-Venezia Giulia, Liguria, Lombardia, Piemonte, Trentino-Alto Adige, Valle d'Aosta, Veneto).
  • The tariff runs for 20 years from the date the system enters commercial operation and stays unchanged throughout.
  • On top of the premium tariff, the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.) pays the valorisation payment set by ARERA on self-consumed (The energy the system produces and you use on site, instead of feeding it into the grid.) energy (the refund of certain components of the bill).
  • The energy fed into the grid stays yours: you can sell it on the market or transfer it to the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.) under Ritiro Dedicato (The GSE scheme that buys the energy you feed into the grid and do not consume.).
  • If you also receive a capital grant (up to 40%), the tariff is reduced in proportion: by up to half where the grant is 40%.
  • The reduction for a capital grant does not apply to energy shared from the delivery points of local authorities, religious bodies, third-sector and environmental protection bodies and individuals.

Requirements for solar PV

  • Each system (or extension) must have a capacity no greater than 1 MW.
  • The systems and the consumers in the configuration must be connected under the same primary substation (the local electricity substation: check it on the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.)'s interactive map).
  • The system must be new or an extension of an existing one; for extensions the tariff applies only to the new section.
  • The system must have entered service on or after 16 December 2021 and, for CERs, after the community was duly set up.
  • For solar PV all the components must be newly built.
  • You must comply with the DNSH principle (Do No Significant Harm to the environment) under the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.)'s Operating Rules.
  • The systems must be at the CER (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.)'s disposal and under its control, even where a third-party producer makes them available.
  • The part of the tariff above the shared-energy threshold (55%, or 45% where there is also a capital grant) must go to consumers other than businesses or to social purposes in the local area: this must be written into the statutes or into an agreement.

Combining it with other incentives

  • Can be combined with the recovery plan grant under the CACER decree: the tariff is reduced in line with the grant obtained.
  • Can be combined with other capital grants up to 40% of the eligible investment costs: the tariff is reduced.
  • Can be combined with other State aid that is not a capital grant, if its value does not exceed 40% of the reference investment cost: the tariff is reduced.
  • Can be combined with no reduction with grants for pre-feasibility studies alone and for the costs of setting up the configuration.
  • Can be combined with no reduction with the ordinary tax deductions for homes (article 16-bis, paragraph 1, letter h, of the consolidated income tax act).
  • Can be combined with no reduction with other forms of public support other than capital grants that are not State aid.
  • Cannot be combined with other operating incentives (paid on the energy), with the Superbonus, or with capital grants or other State aid above 40% of the eligible costs.
  • An alternative to Scambio sul Posto.

How to apply

  1. 1Set up the configuration. A CER (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.) needs a legal entity with compliant statutes (at least two members and two separate connection points). A group of self-consumers needs the building or the apartment building. Check on the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.) map that all the points are under the same primary substation.
  2. 2If you wish, ask for a preliminary check. It is optional and costs 100 euros. The GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.) replies within 60 days with an opinion or with the requirements to follow.
  3. 3Bring the system into service. For CERs the system must enter service after the community has been set up.
  4. 4File the application with the GSE within 120 days. The Referent files it online only, through the SPC-Comunità Energetiche e Autoconsumo portal in the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.) Customer Area, with the documents in Annex 3 of the Operating Rules. If you are late, you lose the tariff for the period between entering service and the application.
  5. 5Wait for the outcome. The GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.) completes its assessment by the last day of the third month after the application. It then pays monthly amounts on account and a balancing payment the following year.

Documents

  • The CER (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.)'s statutes or deed of incorporation with the elements the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.) requires.
  • The mandate to the Referent, where the referent is not the configuration itself.
  • Documentation of the systems and the configuration listed in Annex 3 of the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.)'s Operating Rules.
  • DNSH check sheets.

Mistakes that cost you the benefit

  • Filing the application more than 120 days after entering service: you lose the tariff for the months of delay.
  • Bringing the system into service before the CER (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.) has been set up.
  • Connecting systems and consumers to different primary substations.
  • Including a large business in the CER (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.), or an SME whose main activity is energy.
  • Forgetting the clause in the statutes on allocating the excess tariff to consumers other than businesses or to social purposes.

Official sources

  • GSE — Configurazioni per l'autoconsumo diffuso – Corrispettivi e tariffa, sezioni tariffa premio e cumulabilità
  • GSE — Configurazioni per l'autoconsumo diffuso – impianti ammessi e termine di richiesta
  • GSE — Comunità energetiche rinnovabili – chi può far parte di una CER, statuto
  • GSE — Come accedere – richiesta sul portale SPC e verifica preliminare
  • GSE – testo del decreto — DM MASE 7 dicembre 2023, n. 414, artt. 1, 3, 4, 5, 6 e Allegato 1
  • MASE — DM MASE 16 maggio 2025, n. 127, art. 1, comma 1, lettera f) (Allegato 1, paragrafo 3)

Checked on 19 November 2026

ClosedNon-repayable grant

Recovery plan non-repayable grant for CERs and groups of self-consumers in municipalities under 50,000 residents

This was a non-repayable grant of up to 40% of the costs of renewable energy systems forming part of an energy community (CER) or a group of self-consumers, in municipalities under 50,000 residents. Applications closed on 30 November 2025: you can no longer file new ones.Worth: Up to 40% of the eligible costs (applications closed on 30 November 2025)Closes: 30 November 2025
Show the details

The last window was open from 21 July to 30 November 2025. Systems admitted must enter service within 24 months of the award agreement and in any case no later than 31 December 2027.

Who can claim it

  • Renewable energy communities (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.) (CER).
  • Groups of renewable energy self-consumers acting collectively.
  • The system had to be in a municipality with a population below 50,000 (ISTAT figures at the date of the application). Until 2025 the limit was 5,000 residents.
Who is excluded
  • Remote self-consumers: they can have the premium tariff but not this grant.
  • Systems in municipalities with 50,000 residents or more.
  • Systems whose works started before the grant application.
  • Systems with a capacity above 1 MW.

How much it is worth

  • A capital grant of at most 40% of the eligible costs, within the maximum reference costs set by the CACER decree.
  • Professional costs (pre-feasibility studies, design, works supervision, commissioning and consultancy) can be funded up to 10% of the eligible amount at most.
  • VAT is not eligible, except where it cannot be recovered.
  • Whoever receives the grant also has the premium tariff on the shared energy, but reduced in proportion to the grant.
  • Current funds managed by the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.): 1,041.5 million euros (795.5 million from decree-law no. 19 of 19 February 2026, plus 246 million from law no. 152 of 7 August 2026).
  • As at 30 November 2025, 1,456 million euros had been applied for, more than the funds available. Eligible but unfunded projects are waiting for any reallocation and can in any case have the premium tariff for 20 years.

Eligible costs

  • Building the renewable energy system (components, inverters, mounting structures, electrical components).
  • Supply and installation of storage systems (Batteries that store the energy produced during the day so you can use it when the system is not producing.).
  • Machinery, plant and hardware and software equipment, with installation and commissioning.
  • Strictly necessary building works.
  • Connection to the national electricity grid.
  • Pre-feasibility studies and the costs of setting up the configuration, design, works supervision and safety, commissioning and consultancy: together at most 10% of the eligible amount.

Requirements for solar PV

  • A new system, or an upgrade of an existing one, with a capacity no greater than 1 MW.
  • A system in the area of the primary substation of the configuration it will be part of.
  • A permit for construction and operation and a connection quotation definitively accepted, where required.
  • Compliance with the DNSH principle (Do No Significant Harm to the environment) and with climate tagging.
  • Once built, the system must be part of a CER (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.) or a group of self-consumers with an active contract for the premium tariff.
  • Entry into service within 24 months of notification of the award agreement and in any case no later than 31 December 2027.

Combining it with other incentives

  • It can be combined with the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.)'s premium tariff on shared energy, which is however reduced: by up to half with a grant of 40%.
  • For energy shared by local authorities, religious bodies, third-sector and environmental protection bodies and individuals, the reduction of the tariff does not apply.
  • The ban on double funding of the same costs that applies to recovery plan funds holds here too.

How to apply

  1. 1Applications closed. No new applications can be filed since 30 November 2025. Anyone who already has an award agreement with the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.) follows the steps below.
  2. 2Report the start of the works. Within 30 days of the works starting, the beneficiary reports the date on the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.) portal.
  3. 3Claim payment. Up to 200 kW you can claim an advance of up to 30% and then the balance, or the whole balance. Above 200 kW and up to 1 MW there is also the option of an intermediate instalment of 40%.
  4. 4Report the costs. Follow the Facility CACER Operating Rules and the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.)'s instructions for reporting.

Documents

  • The award agreement with the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.).
  • The permit and the accepted connection quotation, where required.
  • Proof of costs under the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.)'s reporting instructions.

Mistakes that cost you the benefit

  • Starting the works before filing the application.
  • Failing to bring the system into service by 31 December 2027.
  • Not signing the contract for the premium tariff: the grant can be withdrawn.
  • Not reporting the start of the works within 30 days.

Official sources

  • GSE — Comunità energetiche rinnovabili e gruppi di autoconsumatori in Comuni fino a 50.000 abitanti – chi può partecipare, come richiedere, spese, risorse
  • GSE — Configurazioni per l'autoconsumo diffuso – termine del 30 novembre 2025 per il contributo PNRR
  • MASE — DM MASE 16 maggio 2025, n. 127, art. 1 (modifiche agli artt. 1, 7, 8, 10 e all'Allegato 1 del DM 414/2023)
  • MASE — Notizia del 17 luglio 2025: sportello dal 21 luglio al 30 novembre 2025
  • GSE – testo del decreto — DM MASE 7 dicembre 2023, n. 414, art. 6, Allegato 1 par. 3, Allegato 2

Checked on 19 November 2026

Being checkedNon-repayable grant

PREPAC - energy upgrading of central government buildings

A programme run by the Ministry for the Environment and Energy Security for the energy upgrading of buildings occupied by the central public administration. It does not cover local authorities. We are checking whether and how it covers solar PV.

What is missing: We have not yet found in the official guidelines whether solar PV is among the eligible works, nor the dates of the annual window for submitting proposals. The programme covers only central government properties, not municipalities.

Source to check: MASEENEA

What this means for your organisation

As at 19 November 2026 we found no open national call on official sources dedicated to solar PV alone for public bodies: check your Region's calls as well. Under Conto Termico 3.0 solar PV only qualifies as paired work: you must replace the old heating system with an electric heat pump in the same building, and the system must work for self-consumption (the energy produced is used mainly on site).

Compared with businesses and private individuals, a public body has three advantages under Conto Termico. It can apply for an advance booking, that is lock in the grant before the work is finished and receive a payment on account when it starts. It can combine Conto Termico with other public funding up to 100% of the eligible costs, if it owns the building and uses it. In municipalities of up to 15,000 residents, in schools and in public hospitals the general cap on the grant rises from 65% to 100%, always within the ceilings set for each type of work.

Renewable energy communities (CER, groups of users that share the energy produced by nearby renewable systems) are open to the local authorities listed in the ISTAT register of public administrations, such as municipalities, but not to central government. A municipality can be both member and promoter: it makes roofs, carports or land for reclamation available, where the systems stay at the community's disposal. All the systems and all the consumption in one configuration must sit under the same primary substation (the electricity substation serving the area).

For energy communities with systems in municipalities under 50,000 residents there is also a capital grant from the national recovery plan, up to 40% of the investment. The part of the premium tariff above the threshold set by the decree goes to consumers that are not businesses, or to social purposes in the area where the systems stand.

Conto Termico 3.0 can also be used through an energy community the body belongs to: in that case the application to the GSE is filed by the community's representative. It can be combined with the incentives for energy communities within the limits set by the decree on CERs.

Frequently asked questions

Does Conto Termico 3.0 fund solar PV on the town hall or the school?

Yes, but only if in the same building you replace the existing heating with an electric heat pump. Solar PV on its own does not qualify. For the solar part the grant reaches 20% of the eligible cost, within the maximum costs set by the decree, and it cannot exceed the grant for the heat pump.

What is advance booking and who can use it?

It is the route that lets you apply for the grant before or during the work, rather than once it is finished. It is reserved for public administrations and third-sector bodies. You need at least one of the following: an energy audit, an energy performance contract, a public-private partnership contract or a deed awarding the work. When the work starts the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.) pays an amount on account, then possibly an intermediate instalment and the balance. Before counting on it, check on the Portaltermico that advance booking is open.

In small municipalities is solar PV covered at 100%?

The decree raises the Conto Termico cap from 65% to 100% for buildings owned and used by municipalities of up to 15,000 residents, and for public schools and healthcare facilities. The ceilings for each type of work still apply, though, and for solar PV the GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.) rules set 20% of the eligible cost. Before doing the sums, ask the GSE to confirm how the two rules work together on your project.

Can Conto Termico be added to other public funds?

For buildings owned and used by the public administration, yes: Conto Termico can be combined with other public incentives and funding, provided the total non-repayable (A grant that does not have to be paid back.) support does not exceed 100% of the eligible costs. For everyone else the general rule applies: no other state incentives, except guarantee funds, revolving funds and interest subsidies.

Can a municipality be part of an energy community?

Yes. The local authorities listed in the ISTAT register of public administrations can be members or shareholders of a CER (Comunita energetica rinnovabile, a renewable energy community: citizens, businesses and public bodies that share the energy produced by nearby systems and receive an incentive on the shared energy.); central government bodies cannot. A municipality can make roofs and land available for the systems and promote the community locally. The GSE (Gestore dei Servizi Energetici: the state-owned company that runs most of the incentives for renewables.) offers a portal to simulate the potential and a support service for public administrations.

Updates

  1. The GSE has announced the reallocation of the 2026 Conto Termico funds decided by the Ministry of the Environment with directorial decree 72 of 10 April 2026: 450 million euros for public administrations and 450 million for private applicants.

  2. Conto Termico 3.0 has come into force (MASE decree of 7 August 2025). Solar PV qualifies only together with replacing the heating system with an electric heat pump.

  3. The Ministry of the Environment has approved the GSE's Operating Rules for Conto Termico 3.0.

Related pages

Work out how much your organisation saves

Sofia sizes the system around your consumption, applies the incentives you are entitled to and puts you in touch with 2-3 installers. Free of charge.

The information on this page is guidance, current at the date shown and based on the official sources cited. It does not replace the opinion of an accountant or an adviser: before committing to an investment, check your own case with a professional.